The Gauteng High Court (Johannesburg) declared that Eskom's award of a tender to Senta Square to perform control and instrumentation maintenance at Camden Power Station in Mpumalanga between 1 March 2019 and 28 February 2022 was unlawful. However, observes TimesLIVE, the court did not set the contract aside. Instead, it suspended the order it made pending the determination of a just and equitable remedy. Pending the determination of that remedy in September, Senta Square and Eskom must continue to perform on the terms of their agreement to carry out the work. One of the losing bidders for the contract, Siemens, challenged its disqualification from the process. Siemens had been carrying out the work on Eskom’s behalf for at least 12 years, having itself successfully tendered for the work on four previous occasions. Siemens had attained a high score at the technical evaluation stage but was disqualified, apparently because it failed to demonstrate that it had met the ‘prequalification criteria’ specified in the invitation to tender. Tenderers were required to meet one of the three prequalification criteria regarding the minimum B-BBEE status level for their bids to be considered.
However, the court found there was 'no dispute on the papers that Siemens met at least one of the three prequalification criteria – the requirement to commit to subcontract 30% of the work to qualifying small enterprises and qualifying exempt micro enterprise'. Acting Judge Stuart Wilson said: ‘Eskom nonetheless concluded that this was insufficient to meet the criteria as they were set out in the invitation to tender. But that was erroneous. There was accordingly no basis on which the criteria could rationally justify Siemens’ disqualification from the tender process.’
The judge said that tainted the process as a whole and rendered Senta Square’s appointment unlawful and invalid. ‘Given the present fragility of SA’s power distribution system, I am loath to simply set aside the tender process without some sense of what effect, if any, that would have on Camden Power Station and its productive capacity.’ According to TimesLIVE, Wilson said he was alive to the fact that the contract awarded to Senta Square had only just over six months left to run. ‘I need to know how, on the facts, that might affect any order I make to require the tender process to be rerun.’ The judge said Senta Square has not, to date, participated in the proceedings. ‘However, now that the tender process has been found to have been unlawful, Senta may well have a renewed interest in participating in these proceedings. It should clearly be given an opportunity to be heard at the remedy stage,’ he said. Wilson directed the parties to furnish factual information on affidavit on the just and equitable remedy to be granted in light of the judgment, by no later than 3 September.
Kommentare